if dates can't be changed, you push back and ask for more resources to be hired.
As an analogy, a house can be painted by 1 guy over 10 days or 10 guys in 1-2 days.
You cannot always just slap more resources on a task to get it done on time. Something that a lot of management does not seem to understand.